ramana » 15 Aug 2019 22:48
Folks there is some thing wrong with the picture of Kaveri engine if you look from earned value management (EVM) perspective.
Ok. Lets look.
Kaveri revised cost to complete is- 250M (SAFRAN Offset)+ 500 M= 750 M Euros
DRDO has already spent 240 M euros.
So total Kaveri project cost is 240+750M = 990M euros
So in money spent the revised progress is 240/990= 24%
However DRDO says Kaveri is only a few KN short of desired requirement and we have been blue in the face quoting that.
Besides only few months back SAFRAN had said Kaveri is good to fly and should be flight tested.
Agreed its a few KN short.
So obviously there is a huge gap in assessing the Kaveri progress.
Does the revised estimates include cost of fabrication facilities?
We are missing something. And the DRDO scientist whom Pubby talked to did not tell the whole picture.
If the progress is really only 24% it needs a fresh start and can spend the 500M Euros and get on with it.
Basically for 750M Euros one can design a new Kaveri engine and move on.
Someone needs to tell the truth and its not being told.
Top
----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Re: Kaveri & Aero-Engine: News & Discussion
Postby
JayS » 17 Aug 2019 23:15
I just noticed that there was a tender floated by GTRE in Jan Feb 2019 period for Machining, Brazing and TBC for SCB. Most likely for Kaveri. Given the inflow of a number of tenders in last frlew months on various modules, its safe to conclude they are building new prototypes. Are they intending to use SCB now in Kaveri..? Could be. But I am not sure 100%.
Also, another thing I noticed just now, DMRL person during AI2017 Seminar mentioned DMRal has done Preliminary development for 7YSZ ceramic TBC coating using EB-PVD, in collaboration with ARCI. And then a couple of months ago, there was a tender floated by DMRL for setting up a EBPVD facility for TBC. What for..? Industrialization of the Tech..? ARCI was the one perhaps who did the TBC for HTSE1200 SCBs. Looks like a lot is happening in the background.