Even in Nilgiri class frigates, the degree to which the modules are pre-fitted with the equipment is not as high as global standards, so there is a lot of time required for outfitting still.Agreed, but had the initial timeframe of 72 months taken into consideration the time to deliver the weapons systems and sensors which are imported from abroad?
Also, the long lead items required for such a ship are ordered in batches at various stages of construction rather than at once.
From what I know, Vizag class did not utilize modular construction, which changed with P17A frigates.
Construction and rollout speed of P17A is already miles ahead of the Vizag class DDG.