Contract finally signed in September 2021. 30 months for manufacturing and delivering 5 production standard prototypes to the Army. The army will then put these 5 prototypes to trial. After that they will give go ahead to manufacture the rest 113 MK1As.
So Basically it’s not a contract for 118 tanks. Only for 5, then subject to trials, another 113 might be given? Similar to Dhanush, where after 15 Howitzers, army stopped further production of balance 99
 

SARTHAK

Regular Member
Joined
Mar 29, 2020
Messages
632
Likes
1,326
Country flag
is there any final configuration available for mk1a ,alpha defense made a video months ago that the one we saw while deal was signed was not a final configuration
 

Super Flanker

Aviation and Defence Enthusiast
Senior Member
Joined
Nov 9, 2021
Messages
5,057
Likes
12,061
Country flag
is there any final configuration available for mk1a ,alpha defense made a video months ago that the one we saw while deal was signed was not a final configuration
In Which Video did Alpha Defence say the one we saw was not the Final Configuration of Arjun MK1A? By the here is a mock-up of Arjun MK1A Final Configuration.
20220220_122610.jpg

 

shuvo@y2k10

Senior Member
Joined
Apr 4, 2010
Messages
2,653
Likes
6,710
Country flag
So Basically it’s not a contract for 118 tanks. Only for 5, then subject to trials, another 113 might be given? Similar to Dhanush, where after 15 Howitzers, army stopped further production of balance 99
Yes, you can say that. Similar procedure was followed in Arjun mk1 delivery. Thus the protracted timeline.

The MK1A production might take the entire decade (till 2030) to deliver. All this for just 118 tanks. Thus, even if any MK2 is produced and shown to Army right now(2022) and it miraculously passses the trials and order is given for a token 118 no., it will only begin production only in early 2030s, at the earliest.
 
Last edited:

SARTHAK

Regular Member
Joined
Mar 29, 2020
Messages
632
Likes
1,326
Country flag
As per recent IAH (19.2.2022) by Saurav Jha, he has ruled out Arjun mk2 prototype unveiling in Defence expo 2022. We can only expect ground displays of latest iterations of Arjun mk1A in this Defence expo, which we are seeing since 2014.
some upgraded to mk1a like new turret or something else?
 

shuvo@y2k10

Senior Member
Joined
Apr 4, 2010
Messages
2,653
Likes
6,710
Country flag
is there any final configuration available for mk1a ,alpha defense made a video months ago that the one we saw while deal was signed was not a final configuration
Final configurations keeps on changing, and will not be finalized till the 5 production standard prototypes are delivered to the Army by March 2024.
 

India Super Power

Tihar Jail
Banned
Joined
Oct 3, 2020
Messages
2,190
Likes
4,386
Country flag
So Basically it’s not a contract for 118 tanks. Only for 5, then subject to trials, another 113 might be given? Similar to Dhanush, where after 15 Howitzers, army stopped further production of balance 99
What's the update on dhanush last I heard is problems are resolved and production started
I could be wrong
And when will all Dhanush be delivered
 

SUPERPOWER

Senior Member
Joined
Oct 2, 2020
Messages
1,480
Likes
5,278
Country flag
Yes, you can say that. Similar procedure was followed in Arjun mk1 delivery. Thus the protracted timeline.

The MK1A production might take the entire decade (till 2030) to deliver. All this for just 118 tanks. Thus, even if any MK2 is produced and shown to Army right now(2022) and it miraculously passses the trials and order is given for a token 118 no., it will only begin production only in early 2030s, at the earliest.
Hume bohot dukh ho raha hai yeh sunkar aur Hum iski Kadi Ninda karte hai..

SmartSelect_20220220-140409_Google.jpg
 

Super Flanker

Aviation and Defence Enthusiast
Senior Member
Joined
Nov 9, 2021
Messages
5,057
Likes
12,061
Country flag
thanks for this
You are very much welcome bro. By the way could you please send me the link of that Video in which Alpha Defence claimed that it is not the Final Configuration? Please post it here if you can.
 

Super Flanker

Aviation and Defence Enthusiast
Senior Member
Joined
Nov 9, 2021
Messages
5,057
Likes
12,061
Country flag
a short video on difference between riffled and smoothbore guns.

if there are some more advantages or disadvantages of both gun pls mention it

Basically the main difference between a Smooth bore and a Rifled Barrel is that : A rifled barrel has lands and groves that cause the projectile to spin when it exists the muzzle (end of the barrel). A smooth bore is exactly how it sounds, smooth. A smooth bore has no lands and grooves present within its barrel.
rifledvsmooth.jpg

-------------------------------------------------------------------------------
main-qimg-4d5b71f91792204998ab08a8bf38b521.jpeg

(An example of rifling in the 105mm L7A1 gun)
 

Super Flanker

Aviation and Defence Enthusiast
Senior Member
Joined
Nov 9, 2021
Messages
5,057
Likes
12,061
Country flag

Super Flanker

Aviation and Defence Enthusiast
Senior Member
Joined
Nov 9, 2021
Messages
5,057
Likes
12,061
Country flag
Contract finally signed in September 2021. 30 months for manufacturing and delivering 5 production standard prototypes to the Army. The army will then put these 5 prototypes to trial. After that they will give go ahead to manufacture the rest 113 MK1As.
You can't be Serious! 30 months? That means 2.5 years just to deliver 5 Production standard Tanks to the IA? Also are the Gun, Engine and Transmission of the upcoming Arjun MK1A Indigenous or Imported?
 