Is Gun integrated in FOC yet? Have the aerial firing trials been done?4 of 16 FOC Tejas needs to be delivered before end of fiscal year 2019-20.
First 4 (SP-21 to 24) will be probably be delivered together, or by twos in short interval. Last time we saw them in September they were being fitted at jigs, slated to fly in November. The labour strike caused a 3-4week delay.They were to deliver 12 FOC Tejas in 2020-21, so there'll be no overall delay. Defence Decode said SP-33 & 34 are on assembly.
However, after that the line will sit idle for another year or only have to deliver 8 trainer-version Tejas... thus any expansion of production capacity to 24 will apply only to the 83 Mark1A batch.
Mark1A order is yet to be signed until Defexpo-2020 (April), meaning delivery will start only by 2021. Lead time for production has been claimed to be cut from from 12-18 months to 8. IAF still owes HAL ₹20,000 crores. I doubt they have the resources to start production before the order is placed, like they did with LCH.