Well, Shtil would be replaced by VL-SRSAM eventually and maybe the Russians were (as usual) asking for some exorbitant sum of money to effectuate any design changes in the ship? This might have forced Navy to go ahead with arm launchers for now and replace it with VL-SRSAM post-delivery.
On that same page (see source below), they say:-
GRSE P-17A | Launch date | Delivery date | Possible range of durations (in months) between launch and delivery |
---|
Ship 1 | Dec 2020 | 2025 (proposed) | 49-60 |
Ship 2 | Jul 2022 | Early 2026 (proposed) | 42-48 |
Ship 3 | Jun 2023 (proposed) | Late 2026 (proposed) | 36-42 |
First ship of a class is usually delayed. Deliveries speed up in subsequent ships. Nothing new here. Yes they should improve speed for subsequent ships but I think that will happen in NGD and NGF more because of higher indigenous content, especially the weapons and sensors going indigenous.
Same source:-
View attachment 179496
Look at the % of import content in an OPV and in the P-17A. Look at the total number of subsystems. And you'll realize that L&T would hardly fare any better.
Also, L&T is involved in P-17A as well. It is collaborating with GRSE in P-17A.
.
People need to stop falling in this trap that private sector is some panacea.