Re: ADA Tejas (LCA) - III
LCA is actually a compound delta. But yeah, as you said, we need Canards, Horizontal Tails, LERX or Chines along with the delta because of more stringent maneuverability requirements.
Anyway the Mk1's turn performance(STR) is somewhere between a Mirage III at 15-16deg/s and a Mirage-2000 at 18-19deg/sec, obviously at speeds of 300-400 Knots and sea level altitude. According to ACM Naik in his media comments and Air Marshal Wollen's article the turn performance of the LCA is 17deg/s which actually makes sense.
Tejas - Feature - The Light Combat Aircraft Story by Air Marshal MSD Wollen (Retd)
The author, Air Marshal M.S.D. Wollen (Retd) was the chairman of Hindustan Aeronautics Limited from September 1984 to March 1988
From this link.
Delay in commencement of Project Definition (PD) gave ADA time to marshal national resources (80 work centers spread over the country); to construct buildings, recruit personnel and create infra-structure; and to get a clearer perspective of the advanced technologies that could be indigenously developed and those that would need to be imported. The IAF's Air Staff Requirement, finalized in October 1985 is the base document for development.
THe IAF's Air Staff Requirement, finalized in October 1985, is posted here with the authentic link.
The LCA is tailless with a double-sweep delta wing. Its wing span is 8.2 m, length 13.2 m, height 4.4 m. TOW clean 8.500 kg, MTOW 12500kg. It will be super-sonic at all altitudes, max speed of M 1.5 at the tropopause. Specific excess power and g-over load data has not been published. Maximum sustained rate of turn will be 17 deg per sec and maximum attainable 30 deg per sec.
So this is the actual document provided to ADA on 1993 as ASR.
Now the LCA has 14 ton mtow.
It has crossed 22 degree AOA within 85 percent of it's potential capacity with an underpowered 70plus kn engine.
It's present targeted top speed is 1.2 mach at sea level.This has been achieved only in 4 km deep dive as the present 70 plus kn engine is insufficient to reach this speed in level flight.
Another important consideration is because SPIN RECOVERY TEST HAS NOT BEEN COMPLETED , The aircraft is flying within 85 percent of it's original potential.
Because reaching the max AOA is getting close to stall speeds ,The spin recovery test validates the performance of tejas in post stall recovery.SO only after finishing this test will tejas clear it's max AOA.
So the max AOA will be increased only after the conducting of the test.
In all programs this is the norm.
At ceiling limit it is 1.8 mach.
With 90 kn GE-INS6 engine LCA will ahieve much better STR than the so called 17 degree.
This engine will be fitted only on the Serial production aircraft.
SO comparing it with ASR of 1983 with a planned 80 kn engine is basically wrong.
The mk-2 is slated to have 100kn engine.
5ton weapon load .And another 30 percent in crease in range.
Once the JV with snecma produces 90 kn engine, almost all subsystems on it will be indegenised.
SO this achievement is far and above the original specs mandated in the original ASR.
It will have substantially more top speed,more fuel load,more range,more MTOW, more STR,higher AOA,and asea radar and long range BVRs in the mk-2 version ,which won't need as much time consuming flight tests as mk-1.
It would have one of the least RCS fighters in IAF as well.
So this is a signifiant indicator of the basic aerodynamic potential of the design.
If ADA chose some long fuselage ,with high wingloading short wing design in place of the cranked delta,fully relaxed stability,carefree handling FBW,and composite materials(which is chosen by all 5th gens),
all the above specs would have been pipe dreams.
So the LCA that now flies is a completely different aircraft than the mig-21 replacement it was touted to be.
Now it's specs are near grippen C/D if the flight envelope is opened fully with lesser wing loading than grippen.
The mk-2 specs will be even more close to the NG specs.
The author, Air Marshal M.S.D. Wollen (Retd) was the chairman of Hindustan Aeronautics Limited from September 1984 to March 1988. He entered the Indian Air Force in 1947 and was awarded the Param Vishisht Seva Medal (PVSM) for his exemplary role in the 1971 Indo-Pak War. It was during his tenure at HAL that the design and development of the Advanced Light Helicopter and Light Combat Aircraft (LCA) was undertaken. He is considered an authority on LCA, and MIGs in particular. Air Marshal Wollen has authored several papers on aviation and here he talks about Tejas and the reason why it is so important.
The following is the actual timeline of LCA
1983 ADA was formed.
The IAF's Air Staff Requirement, finalized in October 1985 is the base document for development.
Project definition (PD) commenced in October 1987 and was completed in September I988
A Review Committee was formed in May 1989. Experts from outside the aviation industry were included. The general view was that infrastructure, facilities and technology had advanced in most areas to undertake the project. As a precaution, Full Scale Engineering Development would proceed in two phases. Phase 1: design, construction and flight test of two Technology Demonstrator aircraft (TDI & 2); construction of a Structural Test Specimen; construction of two Prototype Vehicles (PVI &2); creation of infrastructure and test facilities. Phase 2: construction of three more PV '5, the last PV5, being a trainer; construction of a Fatigue Test Specimen; creation of facilities at various work centres. Cost of Phase I - 2188 crores, of Phase II - 2,340 crores. Phase I commenced in 1990. However, due to a financial crunch, sanction was accorded in April 1993 and was marked by an upsurge in work.
As a point of interest, a second series of in-flight simulation tests of flight control software took place in July 1996 at Calspan USA on an F-16D VISTA (variable in-flight stability aircraft); 33 test flights were carried out. Another reason for delay was the sanction imposed after Pokhran II in May 1999. Scientists working at Lockheed Martin, USA were sent back; equipment, software and documents were impounded. Herculean efforts brought the FCS software to a standard where the FCS performed flawlessly over 50 hours of testing on TD 1 by pilots, resulting in the aircraft being cleared for flight in early 2001.
The LCA is tailless with a double-sweep delta wing. Its wing span is 8.2 m, length 13.2 m, height 4.4 m. TOW clean 8.500 kg, MTOW 12500kg. It will be super-sonic at all altitudes, max speed of M 1.5 at the tropopause. Specific excess power and g-over load data has not been published. Maximum sustained rate of turn will be 17 deg per sec and maximum attainable 30 deg per sec.
The fighter that was in the works in 1970 was MARUT.Not LCA.
The first funding for the aircraft TD-1 came in 1993 due to severe Financial crunch in the early nineties.
Previously 500 cr was given on 1989 ,which went into establishment of infra and testing facilities and labs for ADA.
SO saying LCA program started in 1970s and it's designers are working on it for 45 years is a motivated lie.
TD-1 won't walk out of the ADA labs with it's own legs in 1995 , just because these 500 cr worth of labs and infra was set up in 1989.
Phase -1 commenced in 1990 with 2180 cr is the official statement .But it was only peper work because due to severe financial crisis in the i990-93 period funds for construction of TD-1 was not released.
The first funding of the prototype TD-1 was received in 1993.
In 7 years the TD-1 flew on 2001 with complete fly by wire software.
I have repeated it more than 10 times in this forum.
But the same absurd cock and bull story that LCA is in the works for 45 years and it is 30 years late is being repeated again and again.
again from the samw article.
In the late eighties India's aircraft Industry was not as advanced as Sweden's; and yet India follows a more arduous design/development route for its LCA, compared to Sweden for its JAS-39 Gripen. The Gripen embodied a far higher percentage of foreign, off-the-shelf technology, including its RM-12 engine (improved GE F404). France (Dassault Aviation) built and exhaustively flew a demonstrator aircraft (Rafale-A) before embarking on construction of Rafale prototypes. Over 2,000 flights were completed by September 1994 when first Flight of a production Rafale was still 20 months away. At that point of time, Dassault Aviation had built or flown 93 prototypes, of which at least fifteen went into production after sixteen years elapsed from 'first-metal-cut' of the Rafale demonstrator to entry into service.
It is unlikely that the LCA will attain initial operational clearance (IOC) before 2010.When it is achieved, it will be an industrial success of magnificent proportion, and is sure to receive the acclaim it deserves.
It achieved IOC with much higher specs than the original ASR.
Tejas - India's Light Combat Aircraft - Official Website