Indore metro -

The construction of the 6.3 km long metro viaduct, including 2 monsoon seasons, was completed in just 484 days.

🔸The track laying was completed in 4 months.
🔸The construction of 3 track turnouts was completed in just 27 days, which is a record in the country.
🔸The three turnouts of the track were electrified in 8 days.
🔸The construction of the metro rail coach was completed in just 5 months after design approval.
🔸The entire work of the traction third rail system was completed in just 45 days.
🔸Additionally, 4 escalators were installed in 23 days.
____________________
 

Suryavanshi

Cheeni KLPDhokebaaz
Senior Member
Joined
Jun 5, 2017
Messages
16,330
Likes
70,182
Salary deduction.

Guy should be dismissed from his job. There are reasons to have SOP for Pilots in aviation. Same things should be implemented for loco pilots with respect to handling.

Guy placing his bag on control panel is a bad start.


Hope RB do something useful
Sarkari chamarchods don't get dismissed only suspension.
 

Physx32

Senior Member
Joined
Feb 28, 2019
Messages
1,507
Likes
9,984
Country flag

FalconSlayers

धर्मो रक्षति रक्षितः
Senior Member
Joined
Oct 14, 2020
Messages
28,076
Likes
194,630
Country flag
Were metro projects in UP funded by centre? If yes then its a valid question as to why Tier-1 cities like Chennai have stalled metro work while cities in UP that are not just small but also poorer have operational metros built quickly.
 

Blademaster

Senior Member
Joined
Aug 19, 2009
Messages
9,597
Likes
27,774
Were metro projects in UP funded by centre? If yes then its a valid question as to why Tier-1 cities like Chennai have stalled metro work while cities in UP that are not just small but also poorer have operational metros built quickly.
That's because Chennai is in Tamil Nadu and is controlled by DMK who is rabidly anti-hindu. Why give them any sops for free?
 

vin bharat mahan

Kumaoni, Uttarakhand
Senior Member
Joined
Jan 7, 2023
Messages
1,195
Likes
3,943
Country flag
Were metro projects in UP funded by centre? If yes then its a valid question as to why Tier-1 cities like Chennai have stalled metro work while cities in UP that are not just small but also poorer have operational metros built quickly.
dont know state or center who r paying for metros....but let compaire UP nd tamilnadu metro:-
1:- UP
total build - lucknow = 23 km.
kanpur = 9 km.
- 23+9 = 32 km.
under construction - agra = 30 km.
approved - meerut = 15 km.
gorakhpur = 28 km.
so total metro will be = 23+9+30+15+28
= 105 km.
we r not taking praposed metro project here.
2:- tamilnadu
total build - only in chennai
blue line = 33 km.
green line = 22 km.
- 33+22 = 55 km.
under construction -
purple line = 46 km.
orange line = 26 km.
red line = 45 km.
total = 46+26+45 = 117 km.
so total metro will be = 55+117 = 172 km.
so clearly UP is making different short metro (105 km) in different cities...meanwhile tamilnadu is making (172 km) 67 km more lengthy metro than UP in only Chennai. dont know why they r crying. 😂🤭
 

ezsasa

Designated Cynic
Mod
Joined
Jul 12, 2014
Messages
32,383
Likes
150,145
Country flag
Were metro projects in UP funded by centre? If yes then its a valid question as to why Tier-1 cities like Chennai have stalled metro work while cities in UP that are not just small but also poorer have operational metros built quickly.
Kochi metro funding pattern, most of the funding comes from state govt and external loans.
Screenshot 2023-10-05 at 12.28.43 PM.png
 

RoaringTigerHiddenDragon

Senior Member
Joined
Sep 5, 2020
Messages
4,115
Likes
17,560
Country flag
dont know state or center who r paying for metros....but let compaire UP nd tamilnadu metro:-
1:- UP
total build - lucknow = 23 km.
kanpur = 9 km.
- 23+9 = 32 km.
under construction - agra = 30 km.
approved - meerut = 15 km.
gorakhpur = 28 km.
so total metro will be = 23+9+30+15+28
= 105 km.
we r not taking praposed metro project here.
2:- tamilnadu
total build - only in chennai
blue line = 33 km.
green line = 22 km.
- 33+22 = 55 km.
under construction -
purple line = 46 km.
orange line = 26 km.
red line = 45 km.
total = 46+26+45 = 117 km.
so total metro will be = 55+117 = 172 km.
so clearly UP is making different short metro (105 km) in different cities...meanwhile tamilnadu is making (172 km) 67 km more lengthy metro than UP in only Chennai. dont know why they r crying. 😂🤭
Who said the center finances UP metros? TamilNadu politicians are known to speak lies after lies. It is in their blood.
Kanpur metro if financed by UP Govt through a loan agreement with European Investment Bank:
.
Lucknow and Agra are also part financed by EIB.
Also, UP does not have a metro city as Capital although the Lucknow-Kanpur area needs to be connected by expressway and RRTS and made into a mega industrial metro region. Madhya Pradesh is the same way: Bhopal-Indore corridor must be connected this way: expressway +RRTS.
But Chennai is a metro and will have a big metro network. And the central government has directly funded it.
 

RoaringTigerHiddenDragon

Senior Member
Joined
Sep 5, 2020
Messages
4,115
Likes
17,560
Country flag
Ya'll Nibbiars

Cuffe Parade reclama must be completed and land opened up for mixed use retail and commercial. The amount of tax revenues to Mumbai through this development is massive. Give good money and build a nice, modern pier for the fishermen as compensation. Why do they have to fish only in the reclamation area? This is a fake claim that has stalled the project for decades. We really need a party even more nationalistic than BJP or let Yogiji become PM. The BJP under Modi is simply afraid to do many things. Meanwhile Yogiji has completely revamped Ayodhya by demolishing useless encroachments and expanded all roads. The city also now has a world class train and airport. All those crying were given excellent compensation and asked to cooperate or the bull dozer was sent.
 

FalconSlayers

धर्मो रक्षति रक्षितः
Senior Member
Joined
Oct 14, 2020
Messages
28,076
Likes
194,630
Country flag
Noida International Airport will have 5 million passengers per annum in first year of operations. Will become 12 million passengers per year in 2 years as per projections. Wonder how much decline in passenger traffic will Delhi face due to this airport.


1696498423404.png
 

RoaringTigerHiddenDragon

Senior Member
Joined
Sep 5, 2020
Messages
4,115
Likes
17,560
Country flag
Noida International Airport will have 5 million passengers per annum in first year of operations. Will become 12 million passengers per year in 2 years as per projections. Wonder how much decline in passenger traffic will Delhi face due to this airport.


View attachment 224982
No decline. Delhi NCR is on target to become a 40 million+ population zone with a PCI of at least $15000 by 2030. That is huge plus NCR would be a hub of industry and air connections. If anything Noida airport would need to be accelerated and fully built up with at least 4 runways by 2030.
 