@Kunal Biswas I know U know more than what i can ever know but sir I have a humble request to not call it a troll as i am not trolling...
16 per year will be started from 2019, 25 per year will be from 2021 ..
I suggest people need to keep their trolling habits else where ..
I was not active for some time but I still know a little....
Given the single production line/Assembly line the numbers suggested here are not valid.
Few factors :
1) Few Changes are still in taking place and are not finalised.
2)IOC standard 20 in manufacturing given the current rate will be completed by 2018-19.
3)FOC standard will have changes which will again lead to some drop in production rate . FOC is expected next year and it has been already few years we have been waiting for it.
4)There will be dependencies on foreign supplier which ussually are teh main cause of delays.
5)IF FOC is acheived next year it will take another 4 years to get them delivered that will by 2022-23.
6)2021 the timeline set by HAL for advnaced Tejas so FOC fits the timeline.
7)Given the changes being handled and made by HAL It will not be possible for them to have a streamlined manufacturing and as per my information the current production line if ideally used has a ability to roll out 16 per year.
Sir i have worked on Aircrafts and very well do understand how the timelines are set and what is reality.
I had counted all these factors when i quoted any of the numbers i suggested .
Going by the timeline of deliveries suggested by you
2016 4
2017 8
2018 8
2019 16
2020 16
2021 25
2022 25
2023 25
By 2023 total 127 manufactured.
i will be really happy if they achieve this but this is just on paper and not ground reality.
Note: I am not expecting any second production line yet.
As last I will again request humbly that whatever I say are my views with some basic knowledge and not TROLLS.