Only partially true:
The first Light Combat Aircraft (LCA) – Tejas squadron has been formed on 1st July, 2016 with two LCA Initial Operation Configuration (IOC) Series Production Aircraft. Further, 18 more aircraft in IOC standard are planned for induction by 2018-19. This would be followed by 20 more aircraft in Final Operation Configuration (FOC) standard, which are planned for induction from year 2019.
The total expenditure incurred on development of Tejas LCA Mk-I aircraft, as on 30th June, 2016 is Rs.8042.46 crores. The total initial sanctioned cost for Full Scale Engineering Development (FSED) for LCA was Rs.5489.78 crores which was later escalated to Rs.9121.07 crores.
The indigenous content of LCA is about 70% and import content is about 30%. The aircraft is indigenously designed and developed and the technology for production of this aircraft is available in the country.
LCA Tejas shall be an important part of IAF’s fighter aircraft inventory filling up the lightweight category of fighters and shall be effectively used for air defence and for battlefield air strikes.
DM/NAMPI/RAJThis information was given by Defence Minister Shri Manohar Parrikar in a written reply to Shri Ram Kumar Kashyap and Dr. R Lakshmanan in Rajya Sabha today.
In-flight refuelling probe testing to begin soon on LCA-Tejas
View attachment 9541
A nearly year ago UK based Company “Cobham” handed over in-flight refuelling probe for integration with LCA-Tejas MK-1 and now HAL is planning to start the first trial runs in next few weeks said informed sources close to idrw.org . Limited Series Production-8 (LSP-8) stopped flying from January this year and has been already integrated with supplied in-flight refuelling probe and land-based trials have been carried out after structural modification were performed on LSP-8 for probe integration which also saw software upgrades to enable fuel sensors to detect mid-air fuel supply and to show correct fuel capacity to pilots. LSP-8 will start flying again in next few weeks to conduct carriage trials before mockup dry trials will begin wherein the first phase IAF’s Ilyushin IL-78 air-to-air refuelling tanker aircraft and LSP-8 will carry out mockup mid-air refuelling where both aircraft will fly in close proximity to record and study behavior of the tanker’s fuel-transferring systems in the vicinity of the probe and the handling qualities of the aircraft. The second phase will see actual contact with the fuel transferring systems of tanker with the in-flight refuelling probe of LCA-Tejas aircraft but no fuel transfer will actually take place , tests will be repeated till it achieves 2-5 minutes in contact with tanker which is actual fuel transfer time usually taken by tanker to pump fuel into a fighter jet. Wet runs trials will be followed after completion of Dry run trials where actual fuel transfer will take place which may happen only in next year . Integration and demonstration of mid-air refuelling probe on LCA-Tejas are one of the key requirement to obtain Final Operational Clearance (FOC) . First, 20 IOC-II certified LCA-Tejas MK-1 will initially be produced and delivered without in-flight refuelling capacity but will be upgraded at a later stage since all aircraft will come with provision for pumps and fuel lines for IFR integration at a later stage.
idrw.org . Read more at India No 1 Defence News Website , Kindly don't post our articles on other copycat websites http://idrw.org/in-flight-refuelling-probe-testing-to-begin-soon-on-lca-tejas/#more-102365 .
What do you want to say on Modi + LCA ?I am not sure if he is honest either. self praising and propaganda are the new norms now. I somehow knew it from the beginning about this hyperbole government.
No soon as FOC is achieved, They can focus on MK1+ which shall be a real deal. You can induct tejas but most important of all is to make them war worthy.I was a meek spectator of this forum but sometimes one has to say. Tejas has been in development for 20+ years no one blamed UPA for that matter and I can be certain that had UPA continued we wouldn't have inducted those 2 either.
DM said he did 18+ RT conference with stakeholders to get it inducted yet people are so hasty and fidgety. Tejas aims to get FOC by March 2017, I am not sure whats the fuss then? Even if they do wet trial by early next year they have enough window to get it rolling. Moreover there are only handful of major addons in 1A, other major aviation tests are already done.
Meanwhile the first thing they need to get out is 18+ IOC Tejas before talking about FOC, and even if they get FOC by March next year they don't have inventory to crack things out. Technically with their current capacity it will take 2+ years for them to complete 1st squadron. So first FOC plane should roll out by mid-end of 2018. FOC or not makes no difference.
I dont want to delve deeper into what the government has done, which is a lot, but sometimes people just can't be happy. When they curb black money people stage protest and when they not people accuse them, its like some people can never be satisfied no matter what.
Moreover HAL is not controlled and managed by government directly, HAL has bite off more than they can chew.
@sukhish - SO you have a crystal ball? Mind sharing some insights as well.
JM2C.
Thread starter | Similar threads | Forum | Replies | Date |
---|---|---|---|---|
AERO INDIA 2021 | Science and Technology | 308 | ||
ADA Tejas Mark-II/Medium Weight Fighter | Knowledge Repository | 6 | ||
ADA Tejas Mark-II/Medium Weight Fighter | Indian Air Force | 8939 | ||
P | ADA DRDO and HAL Delays a threat to National Security | Internal Security | 20 |