courtesy RANDY M MP.net
MDL believes that, since Project 15-B is a follow on of the 15-A, the design and planning period will be less than 1½ years. Once the design is finalised, the navy wants the first destroyer to roll out within four years, with the others completed at one-year intervals. By that ambitious timeline, if the order is placed on MDL by end-2009, the first 15-B destroyer would be commissioned in mid-2015.hope they plan in advance for a project 15c-desi version of aegis class destroyers.anyways when are the p-15b going to be inducted?
2018,2020,2022,2024 are the respective delivery years.MDL believes that, since Project 15-B is a follow on of the 15-A, the design and planning period will be less than 1½ years. Once the design is finalised, the navy wants the first destroyer to roll out within four years, with the others completed at one-year intervals. By that ambitious timeline, if the order is placed on MDL by end-2009, the first 15-B destroyer would be commissioned in mid-2015.
i believe it will be in 2017
MDL believes that, since Project 15-B is a follow on of the 15-A, the design and planning period will be less than 1½ years. Once the design is finalised, the navy wants the first destroyer to roll out within four years, with the others completed at one-year intervals. By that ambitious timeline, if the order is placed on MDL by end-2009, the first 15-B destroyer would be commissioned in mid-2015.
i believe it will be in 2017
2018,2020,2022,2024 are the respective delivery years.
Read it in a article for the delivery of shafts from Russia.
Would try to dig it up and link it here.
Russia to help India build 4 guided-missile destroyers | Russia & India ReportThe ships are due to be built sequentially in June 2018, 2020, 2022, and 2024.
-------------------Laid down -------------LaunchedMDL believes that, since Project 15-B is a follow on of the 15-A, the design and planning period will be less than 1½ years. Once the design is finalised, the navy wants the first destroyer to roll out within four years, with the others completed at one-year intervals. By that ambitious timeline, if the order is placed on MDL by end-2009, the first 15-B destroyer would be commissioned in mid-2015.
i believe it will be in 2017
easy on the caps dude and i am not the one building the ships i am just another tax payer like you-------------------Laid down -------------Launched
INS Kolkata----27 September 2003--30 March 2006
INS Kochi------25 October 2005------18 September 2009
INS Chennai---21 February 2006-----1 April 2010
cost of each ship escalated to 1.9Bn$ each (11662 crore each) still no sea trials , commissioning ,
sat saal se chat rahe hai kya???
how can i complain about it to you,that was public expression.easy on the caps dude and i am not the one building the ships i am just another tax payer like you
L&T make universal missile launchersDrdo or any other Private Firm should try to build a universal Vls capable of launching AShMs, LACMs, SAMs... In this way we can accomodate more missiles on a single ship and probably can keep the same tonnage and design that we have now.
Some of the launcher in L&T's range of products are:
Universal Missile Launcher : a multi-mode launcher
Multi Barrel Rocket Launcher: a high-positioning-accuracy platform with programmable option for Single / Salvo firing
Anti-Tank Guided-Missile Carrier
Quick Reaction Surface-to-Air Missile Launcher
The Gas Turbine engines are coming from Ukraine..